Over the course of the project, the external fit out company experienced some unforeseen issues which unfortunately set the deadline back by a matter of months. As a result of this, we had to find a way to hold and store the furniture items which had been ordered and delivered on schedule. The Penketh Group project management team were able to think on their feet and secure a storage facility where we held the furniture until the site was eventually ready for furnishing.
Securing storage meant that the fit out team could continue work safely and eliminated any further disruption to the project. The team were also able to call upon our strong relationships with manufacturers and suppliers to negotiate and hold prices to deliver the brief to budget.
We really enjoyed working with Bridge Architects and the team at Alderley Park on transforming the Glasshouse hub and look forward to hopefully working closely together again in the near future!